Install Ties and Gates:

The last step is to tie off all rails and posts and hang the gates. Take care to center the top diamond of the fence on the top rail. Tie rails first and posts last. Use nine tie wires per line posts and five tie wires per horizontal rail in between line posts. Click HERE for an animation of how to tie a tie wire.

Gate hardware is included with the purchase of our tennis court kits. Hinges and latches are fairly self-explanatory. Both simply bolt into place. Secure bottom box hinge first. Make a mark for the second box hinge and bolt in place. Slide gate leg into box bottom box hinge and lift into the top one. Fit with hinge coupler and your gate is hung. If using a standard fork latch, bolt at a convenient height.